| Datacenter Maintenance Outage Thursday @1am PST | Login: Visitor | LOGIN | Help |
![]() |
IT Priorities SysAdmins Priorities |
|
| LIST ALL |
Zero Day Alert - Work with InfoSec - InfoSec / Francis, Chris - Operations - Due 2018-02-19
|
half servers are finished |
CCRI Preparation - Security / Murphies, Mike - Operations - Due 2018-06-24
|
Need to start reviewing all STIGS for CCRI. |
MCR 1123 - Upgrade Centrify - Linux / Shakes, William - Change Request - Due 2018-03-12
|
Almost done! contacted Support, there was an issue |
Mike Mellows - Login Issue - Windows / Francis, Chris - Support - Due 2018-06-19
|
Could be security or Pebkac |
Purchase Vegas Network Racks - Network / Lewis, Trevor - Management - Due 2018-06-20
|
Need to push through rack order and work with Vendor |
Rebuild DNS in Vegas - Linux / Shakes, William - Project - Due 2018-03-19
|
Old servers are being retired, rebuild DNS |
Backups Broken on Billings - Linux / Lewis, Trevor - Operations - Due 2018-02-19
|
I cannot figure it out.assigning to kirk |
Nessus Scan - Saturday - InfoSec / Account, Demo - Operations - Due 2018-04-21
|
InfoSec will be scanning Los Angeles datacenter. They brougt 2 servers down last time. On-call should be ready and aware! |
Finalize Red Hat support - DatacenterOps / Lewis, Trevor - Management - Due 2018-03-30
|
Continue working with Red Hat to finalize support |
Windows Dev Patching Vegas - Windows / Account, Demo - Operations - Due 2018-04-10
|
Windows Patching Double check withe ASM users that have special needs for patching. * Chuck Stephans cant be patched until end of month. |
Hire New Sr Linux Admin - Human Resources / Lewis, Trevor - Management - Due 2018-02-19
|
Work with recruiters to find new a new Senior Level Admin |
Move Servers lax01-music01-10 to Rack 22 - DatacenterOps / Francis, Chris - Operations - Due 2018-08-25
|
Schedule and coordinate with the server and service owners. Be sure to write Change management! |
MCR128 - Linux Production Patching - Linux / Michaels, David - Change Request - Due 2018-04-07
|
Deploy Linux Production Patching Compile List for management approval |
Build New Domain Controller in Los Angeles - Windows / Account, Demo - Build - Due 2018-04-01
|
Build a new Primary Domain Controller due to hardware upgrade |
Time Service Upgrade - Network / Francis, Chris - Operations - Due 2018-04-10
|
Install new time servers in LA and LV |
Install VM tools across everywhere - DatacenterOps / Francis, Chris - Project - Due 2018-08-07
|
Ensure that VM Tools is installed or upgraded where necessary |
PKI Assessment - Security / Murphies, Mike - Project - Due 2018-07-02
|
MS onsite to provide PKI Assessment |
Employee Reviews - Human Resources / Lewis, Trevor - Management - Due 2018-07-01
|
Begin recording events, achievements and failures. |
Evaluate Splunk for Vegas - Linux / Shakes, William - Project - Due 2018-09-19
|
Evaluate in Las Vegas for benefits and cost |