Zero Day Alert - Work with InfoSec - InfoSec / Francis, Chris - Operations - Due 2018-02-19 |
half servers are finished | CCRI Preparation - Security / Murphies, Mike - Operations - Due 2018-06-24 |
Need to start reviewing all STIGS for CCRI. | MCR 1123 - Upgrade Centrify - Linux / Shakes, William - Change Request - Due 2018-03-12 |
Almost done! contacted Support, there was an issue | Mike Mellows - Login Issue - Windows / Francis, Chris - Support - Due 2018-06-19 |
Could be security or Pebkac | Purchase Vegas Network Racks - Network / Lewis, Trevor - Management - Due 2018-06-20 |
Need to push through rack order and work with Vendor | Rebuild DNS in Vegas - Linux / Shakes, William - Project - Due 2018-03-19 |
Old servers are being retired, rebuild DNS | Backups Broken on Billings - Linux / Lewis, Trevor - Operations - Due 2018-02-19 |
I cannot figure it out.assigning to kirk | Nessus Scan - Saturday - InfoSec / Account, Demo - Operations - Due 2018-04-21 |
InfoSec will be scanning Los Angeles datacenter. They brougt 2 servers down last time. On-call should be ready and aware! | Finalize Red Hat support - DatacenterOps / Lewis, Trevor - Management - Due 2018-03-30 |
Continue working with Red Hat to finalize support | Windows Dev Patching Vegas - Windows / Account, Demo - Operations - Due 2018-04-10 |
Windows Patching Double check withe ASM users that have special needs for patching. * Chuck Stephans cant be patched until end of month. | Hire New Sr Linux Admin - Human Resources / Lewis, Trevor - Management - Due 2018-02-19 |
Work with recruiters to find new a new Senior Level Admin | Move Servers lax01-music01-10 to Rack 22 - DatacenterOps / Francis, Chris - Operations - Due 2018-08-25 |
Schedule and coordinate with the server and service owners. Be sure to write Change management! | MCR128 - Linux Production Patching - Linux / Michaels, David - Change Request - Due 2018-04-07 |
Deploy Linux Production Patching Compile List for management approval | Build New Domain Controller in Los Angeles - Windows / Account, Demo - Build - Due 2018-04-01 |
Build a new Primary Domain Controller due to hardware upgrade | Time Service Upgrade - Network / Francis, Chris - Operations - Due 2018-04-10 |
Install new time servers in LA and LV | Install VM tools across everywhere - DatacenterOps / Francis, Chris - Project - Due 2018-08-07 |
Ensure that VM Tools is installed or upgraded where necessary | PKI Assessment - Security / Murphies, Mike - Project - Due 2018-07-02 |
MS onsite to provide PKI Assessment | Employee Reviews - Human Resources / Lewis, Trevor - Management - Due 2018-07-01 |
Begin recording events, achievements and failures. | Evaluate Splunk for Vegas - Linux / Shakes, William - Project - Due 2018-09-19 |
Evaluate in Las Vegas for benefits and cost |